Gym - Bleacher Progress - December 23, 2009
|
Gym - Bleacher Progress - December 23, 2009
Now that the gym floor is finished, installation has begun on the stadium bleachers that were donated to us. The frame has been assembled, the floor pieces have been laid out, and the additional electrical wiring needed has been run. Over the next two weeks the frame will be attached to the wall, the floor pieces will be fastened down, and the seats will be installed.